Kentfield Pump Station 15 Improvements

Kentfield Pump Station 15 Improvements

Project Schedule

Mobilize:  Summer 2018

Complete:  Fall 2019

Kentfield_Map










July 2019 Updates


  • The pump station was returned to normal operation to ensure system reliability and public safety during wet weather,
  • The Contractor will return soon to complete the project. 
  • The contractor will not need to install or operate a bypass pumping system when they return.

Project Information and Construction Notices

Please see individual project construction notices when posted for information about allowable work hours in each work area.


  • Click here to view the Project Information Sheet.
  • Click here to view Construction Notices as they become available.


Project Map

Please see the Current Infrastructure and Upcoming Capital Projects map below or click here to view both current and completed CIP projects on an interactive map. You can also go to the project pages listed on the left of this page for more information about other CIP projects that are under construction or scheduled to begin soon.


Project Contacts

Project Manager - James Smith, P.E.

Email:  jsmith@rvsd.org

Call:  415-870-9771


Construction Manager - Joseph Easterbrook, P.E. 

Email:  joseph.easterbrook@psomas.com 

Call:  707-489-4376


Project Summary


The Kentfield PS 15 Improvements will replace old or outdated system infrastructure and enhance local wastewater system reliability and efficiency. The project is being completed at a cost of $2 million.


Located in Kentfield, the pump station is along Marin County Bicycle Route 20, adjacent to Corte Madera Creek and just south of Stadium Way.


Project Construction Will Include

  • Use of Marin County Bicycle Route 20 for equipment/trucks to access the Pump Station.
  • Rehabilitation of portions of the existing pump station, including inlet channel modifications, concrete repairs, manhole modification and rehabilitation and the installation of new electrical equipment.
  • Bypass pumping connections and ancillary work. 

What You Can Expect

Once the contractor is ready to deliver and install the new pump station equipment, several pickup trucks will arrive and depart each day along Marin County Bicycle Route 20. Trucks will enter from Bon Air Road and travel along Corte Madera Creek to the Pump Station. 


Please expect noise, dust, partial bike lane closures and travel delays near the work site during construction activity. All construction equipment and materials will be stored within the fenced area surrounding the Pump Station. Local emergency access will be maintained at all times.


  • Noise, Dust, Lane Closures and Detours, Travel Delays

More Information About Construction Projects


Visit RVSD.org/construction

To find out if there will be construction in your neighborhood


Notify Me at RVSD.org/notifyme and click to select the Construction Updates you want.


Email Construction@rvsd.org

To leave a message or request being added to the project email list


Call RVSD at 415-259-2949. Our office staff are available Monday - Friday from 7:30 a.m. to 4 p.m. 

We can assist you with emergency service 24 hours per day, seven days per week.


RVSD APPRECIATES your patience as we fulfill our commitment to making strategic long-term infrastructure improvements.

RVSD_CIPMap_7.15.19-01